Q2 FY27 · NSE: VSSL

Vardhman Special Steels

Results filed 27 October 2026 · Market cap ₹3,178 crore · PE 19.7

GrowthGuidance maintainedTranscript read

Revenue
+38.8%
on a year ago
EBITDA
+52.7%
on a year ago
Profit to shareholders
+51.9%
on a year ago
EBITDA margin
11.5%
−0.5 pts on last quarter

Vardhman Special Steels delivered robust Q2 FY27 results with revenue from operations climbing 38.8% YoY to ₹600.05 crore and PAT rising 51.9% to ₹52.49 crore on strong festive volumes and price realization resets. Growth initiatives advanced with the groundbreaking of the ₹475 crore Ludhiana forging facility, while the upcoming greenfield steel plant faces cost escalation beyond ₹2,000 crore, prompting a proposed capital structure shift to 1:1 debt-to-equity and a planned rights issue in H2 CY2027. Working capital stretched due to back-ended shipments and extended customer terms, driving trade receivables to ₹410.61 crore, while core existing operations remain constrained at 300,000 tonnes pending formal regulatory approval for brownfield expansion.

Vardhman Special Steels Limited, Q2 FY27₹ crore, standalone
Q2 FY27Q1 FY27vs previous quarterQ2 FY26vs a year ago
Revenue600486+23.5%432+38.8%
Operating profit (EBIT)59.548.86+21.8%37.18+60.0%
Operating margin9.9%10.1%−14 bps8.6%+131 bps
Other income14.749.86+49.5%11.22+31.4%
Exceptional items00–0–
Profit before exceptional items and tax70.5655.4+27.4%46.5+51.7%
Profit to shareholders52.4941.19+27.4%34.56+51.9%
Earnings per share (₹)5.434.26+27.5%3.61+50.4%

Source: Vardhman Special Steels Limited’s filing to NSE, 27 October 2026. Operating profit is revenue less every expense except interest, so it leaves out other income and exceptional items. n.m.: not meaningful, because the earlier figure was zero or negative, or the latest one is a loss.

What stood out

  • Significant capex inflation and scope expansion for the new greenfield steel plant beyond earlier ₹2,000 crore estimate, prompting a revision in financing to 1:1 debt-equity and a planned rights issue in H2 CY2027
    SourceTranscript original page 4 (Sachit Jain): 'Land is definitely more expensive than we had envisaged as well as for the equipment... project cost will be higher than the INR2,000 crores that we had envisaged... we are diluting a bit more than required. And therefore, we may look at a 1:1 debt equity... For the equity part, we'll be doing a rights issue, which will happen in the later part of next calendar year, second half of next calendar year.'
  • Board is considering suspending dividends for 3-4 years to fund growth capex internally instead of paying tax and calling for capital
    SourceTranscript original page 4 (Sachit Jain): 'The other thing we are examining, of course, the decision will be taken by the Board, is also to look at examining, suspending the dividend for 3-4 years. It does not make sense to give dividend, pay tax on that, and then ask rights issue for these same investors to put in money and rights issue.'
  • Substantial jump in trade receivables to ₹410.61 crore from ₹277.84 crore in March 2026, driven by back-ended shipments in August–September and extended customer credit terms
    SourcePresentation page 9 (Balance sheet) and Transcript original page 9 (Sachit Jain & Sanjeev Singla): '...incremental sales of 11,000 tons, which happened in the last 2 months, August and September, is leading to this high receivables... In number of days, it has increased by 4 to 5 days only because of some sales to customers who are having a high credit period.'

Guidance

MetricGuidancePeriod
EBITDA per ton
SourceTranscript original pages 5 & 6 (Sachit Jain): 'Our guidance remains INR9,000 to INR12,000 as EBITDA per ton... I will request you not to treat that for now as a standard kind of a thing.'
₹9,000 to ₹12,000 per ton (management cautioned that current Q2 level of ₹11,346 is at the upper band and contains temporary gains)Foreseeable future / annual basis
Sales volume
SourceTranscript original page 6 (Sachit Jain): 'So, we expect sales of about 260,000 tons now for the year. Budget was about 260,000 tons.'
~260,000 tonnes (tracking slightly higher than initial budget)FY27
Existing plant capex
SourceTranscript original page 10 (Sachit Jain): 'It will be about INR150 crores for the existing plant.'
₹150 croreNext 3 years (FY27–FY29)
Brownfield debottlenecking capex
SourceTranscript original page 12 (Sachit Jain): 'It's not substantial, but about INR100 crores, INR115 crores.'
₹100 crore to ₹115 crore (to move from 300k to 360k MTPA upon EC approval)FY27–FY28

Tailwinds

  • Operational cost savings and yield improvements resulting from commissioned Kocks Block and walking-beam reheating furnace
    SourceTranscript original pages 5 & 13 (Sanjeev Singla & Sachit Jain): '...benefit in terms of cost saving from these capex in the second quarter and going forward it will further increase... yields have become better because from a 4.2 meter billet, we have gone to a 5.2-meter billet.'
  • Strong rolled volume expansion, rising 26.84% YoY to 70,440 tonnes driven by automotive festive inventory build-up and market tightness
    SourceMedia Release original page 2: 'The volumes for the quarter stood at 70,440 tonnes (only Rolled Products) as against 55,536 tonnes in Q2 FY26, a YoY increase of 26.84%...'
  • Pricing revisions and tight domestic alloy steel availability due to competitor shutdowns and robust demand
    SourceTranscript original page 3 (Sachit Jain): 'material supply for automotive segment was tighter. And there were 1 or 2 shutdowns, unscheduled shutdowns, from one of the large companies. That led to also a slight shortage in the market, and therefore the pull... we got good price increases in the last 2 quarters which has led to good profits.'
  • Commercialization milestones achieved with European OEM and import substitution orders
    SourceTranscript original page 5 (Sachit Jain): 'we have finally received the approval from the European OE. Mass manufacturing for that has started. Also, on a major import substitution of domestic major... Sales for that will start happening from January.'

Headwinds

  • Input and project cost escalations driven by currency depreciation, raw metal price rises, and elevated freight rates
    SourceTranscript original page 4 (Sachit Jain): 'The rupee has depreciated after the Iran war substantially. Sea freight has gone up, as well as metals have gone up. So, our commodities have gone up. So, the project cost is going to be higher than what we had envisaged.'
  • Expiration of the 7-year state GST incentive scheme as of August 2026
    SourceTranscript original page 5 (Sanjeev Singla): '...because the GST benefit was sanctioned by the government for 7 years. And the 7-year period has over by August, '26. And now we are left with only electricity duty benefit...'
  • Existing capacity bottleneck capped at 300,000 tonnes pending official Environmental Clearance letter for 360,000 tonnes expansion
    SourceTranscript original pages 5 & 7 (Sachit Jain): 'Overall capacity is still constrained by the environment approval of 300,000 tons. We have applied for increasing the capacity to 360,000 tons. We seem to have got a recommendation... But till we haven't received any letters so far.'
  • Customer demand softening observed in the tractor segment
    SourceTranscript original page 14 (Sachit Jain): 'And tractors, what I'm hearing from some of the customers seems to be slowing down a bit.'

New businesses and products

new business · Foundation stone laid in July 2026; commercial commissioning targeted by March 2028

Forging and machining facility forward integration in Ludhiana

Expected benefit
Absorbs ~15,000 tons of internal steel annually at full capacity; Line 1 revenue potential of ~₹300 crore at steady-state with guided EBITDA margins of 15–20%
Risks
Entry into a new suboptimal single-line business; learning curve risks
Timeline
Commissioning by March 2028 (Q3 FY28)
Investment
Budgeted capex of ₹475 crore for Line 1 (management noted final cost may be lower)
SourcePresentation page 30 and Transcript original pages 3, 4, 10, 11 & 12 (Sachit Jain): 'Foundation stone of a forging plant was laid... July end this year... forging plant is expected to come up by March of '28... Initially, it will absorb about 15,000 tons annually at full capacity... Forging, the cost will be lower than what we had budgeted.'

capacity expansion · Equipment finalized; land finalized for SMS; environmental approval filing planned by December 2026; rolling land acquisition ongoing till January 2027

Greenfield special steel plant

Expected benefit
Initial capacity of 500,000 tons with built-in scope to scale to 700,000 tons in Phase 2; enables entry into larger diameter blooms and non-automotive sectors (railways, windmills)
Risks
Substantial capex cost escalations due to land, equipment prices, rupee depreciation, and sea freight
Timeline
Completion by September 2029; stabilization by March 2030
Investment
Higher than the initially envisaged ₹2,000 crore (final figures to be shared by March/April 2027)
SourceTranscript original pages 4 & 12 (Sachit Jain): 'project cost will be higher than the INR2,000 crores that we had envisaged. But we will also have the ability to have a higher production than 500,000 tons eventually... complete the project by September of '29 and stabilization by March of '30.'

new product · Commencing trials at the end of November 2026

Ingot casting pilot for non-automotive specialty steels

Expected benefit
Enables higher-alloy, larger diameter steels for tool & die, oil & gas, and railways to seed markets ahead of greenfield commissioning
Risks
Suboptimal volumes during pilot phase
Timeline
Starting late November 2026; stabilization over couple of months
Investment
Not explicitly broken out (part of existing plant capex)
SourceTranscript original page 11 (Sachit Jain): 'we are starting with ingot casting, which is the route to make specialized steels. This is something that we will start in the end of November, it will start. It will take a couple of months to stabilize, and then we'll figure out the markets.'

capacity expansion · Under implementation

Solar power capacity expansion

Expected benefit
Supplies clean energy (20 MW for existing plant, 2.5 MW for NDT line in forging plant); further reduces carbon intensity and energy operating cost
Risks
Execution and grid synchronization timelines
Timeline
Commissioning aligned with forging plant ramp-up
Investment
Not specified
SourceTranscript original page 4 (Sachit Jain): 'we are now expanding the solar plant by another 22.5 megawatts. 20-megawatt for this will be for the current plant and 2.5-megawatt will be for the NDT line, which is being set up in the forging plant.'

Things to check

  • Significant trade receivables increase of 47.8% over six months (to ₹410.61 crore from ₹277.84 crore), accompanied by prolonged 2 to 3-year lags in receiving cash against accrued government GST refunds
    SourcePresentation page 9 and Transcript original page 9 (Sanjeev Singla): 'So normally it is a lag of 2 to 3 years time lag. So, we are recognizing on accrual basis, but it takes time to get the money in cash from the state government, normally it takes 3 years.'
  • Short-term debt rose to ₹162.93 crore from ₹92.65 crore in March 2026, driven by working capital needs and reclassification of LC discounting creditors under Ind AS
    SourcePresentation page 9 and Transcript original page 7 (Sachit Jain): 'borrowing has been increased to INR162.93 crores as of 30th September... Earlier, there were some creditors which were against discounting of the LCs were clubbed under trade payable.'

How the call went

Management was forthright regarding operational realities, input pressures, and structural changes to the balance sheet financing, but was defensive and dismissive when probed on capex revisions, customer volume allocations, or returns on new initiatives.

Specific or vague
Management offered clear figures regarding production capacity, current EBITDA/tonne, and timeline milestones, but repeatedly deferred capex and capital return details to March/April 2027.
Candour
The CMD was candid about project cost inflation, suboptimal margins in the initial forging line, and moderating expectations from current peak EBITDA/ton levels.
The hard questions
Sachit Jain firmly deflected questions estimating revised greenfield capex and forging unit return metrics (ROCE/EBITDA), cutting questioners off repeatedly to keep to the two-question limit.

What analysts pressed on

  • Quantum of greenfield steel plant capex overrun above ₹2,000 crore and its return profile
  • Sharp run-up in trade receivables and working capital cycle expansion
  • Sustainability of elevated realizations and EBITDA/ton levels
  • Expected timeline and shutdown requirements for the 360,000 tonnes brownfield environmental expansion

Answers that sidestepped

  • Refusal to provide any ballpark percentage increase or capex figure for the expanded greenfield steel project (Transcript original page 10: 'We are not as I said, we're not sharing any information at this point in time.')
  • Refusal to commit to any EBITDA or ROCE metrics for the ₹475 crore forging line (Transcript original page 12: 'Forging, we're not making any comments at this point in time... Give us some freedom to start learning this business before we start committing something.')

Numbers against the story

Management celebrated record sales and 50%+ profit growth, citing structural efficiency gains from the new reheating furnace and Kocks Block; however, reported numbers and commentary clarify that elevated profitability was substantially aided by temporary price increases, inventory benefits carried forward, and a higher GST incentive refund that fully expired in August 2026. Management prudently guided that current unit EBITDA of ₹11,346/t sits near the upper ceiling and normalized sustainable levels remain ₹9,000–₹12,000/t.