Results filed 2 November 2026 · Market cap ₹3,132 crore · PE 35.8
GrowthGuidance maintainedTranscript read
Revenue
+58.4%
on a year ago
EBITDA
+38.5%
on a year ago
Profit to shareholders
+87.0%
on a year ago
EBITDA margin
6.2%
−0.2 pts on last quarter
PSP Projects reported a 58.3% YoY revenue jump to INR 1,113.24 crores in Q2 FY27, supported by accelerated execution across its expanded INR 12,872 crore order book. However, EBITDA margins contracted to 6.21% from 7.10% a year ago, driven by lower-margin structural phase execution and a heavy 72% concentration in Adani Group projects. Receivables of INR 90 crores in Surat Diamond Bourse remain unresolved with no payment commitments, while full-year revenue growth is guided at 30% to 35% with ~7% EBITDA margins.
Source: PSP Projects Limited’s filing to NSE, 2 November 2026. Operating profit is revenue less every expense except interest, so it leaves out other income and exceptional items. n.m.: not meaningful, because the earlier figure was zero or negative, or the latest one is a loss.
What stood out
Significant order book concentration in Adani Group projects on a cost-plus percentage model.Source"Our order book is almost 75% is Adani and 25% is non-Adani. If you understand that we are working with Adani Group as cost-plus percentage only. So all the material cost difference has to be reimbursed by the group." (Transcript, Original Page 7); "Of the total order book within group projects account for approximately 72% (INR9,229) crores, while external projects contribute the remaining 28%." (Transcript, Original Page 3)
EBITDA margins remain compressed at 6.21% despite 58% top-line growth due to project stage mix and Adani contract terms.Source"EBITDA margin is at 6.21%, which was 7.10% similar earlier quarter." (Transcript, Original Page 5); "Is this primarily because the Adani business operates at a relatively lower margin of around 5.5% to 5.7%... Prahaladbhai Patel: Yes, you are absolutely right..." (Transcript, Original Page 10)
Overdue receivables from Surat Diamond Bourse remain stuck with zero recovery commitment.Source"See first I will talk about Surat. No, there is no commitment from their side again... Okay. And SDB amount is INR90 crores, it stays as it is? Prahaladbhai Patel: Yes." (Transcript, Original Pages 11, 12)
Guidance
Metric
Guidance
Period
Revenue GrowthSource"As I mentioned, our current guidance is to deliver year-on-year growth in the range of 30% to 35%... internally, we are targeting growth beyond 30%." (Prahaladbhai Patel, Transcript, Original Page 9)
30% to 35% YoY growth for FY27, with internal target aiming higher; 25% to 30% 3-year CAGR
FY27 & next 3 years
Order InflowsSource"It will be in the range of minimum INR4,000 crores to INR5,000 crores approximately." (Prahaladbhai Patel, Transcript, Original Page 6); "Yes. I am still expecting at the end of the year, overall, we will be in the range of INR5,000 crores plus." (Transcript, Original Page 11)
INR 4,000 crores to INR 5,000+ crores
FY27
EBITDA MarginSource"Yes. We can say it can go upto 7.5%... currently expect margins to be around 7%." (Prahaladbhai Patel, Transcript, Original Pages 6, 11)
Around 7% for full year FY27, potentially reaching 7.5% in H2
FY27
CapexSource"For half year, we have incurred around INR90 crores. So further around INR100 crores we might be incurring... additionally, it should be in the range of 3% to 4% of revenue every year..." (Hetal Patel & Prahaladbhai Patel, Transcript, Original Page 12)
INR 190 crores total in FY27 (INR 90 cr spent in H1 plus ~INR 100 cr in H2); 3% to 4% of revenue annually thereafter
FY27 / FY28
Revenue growth expectations stepped up from 25% to 30-35% on strong H1 run rate, while EBITDA margin guidance lowered towards ~7% from the previous 7.5%-8% band.
Tailwinds
Sharp execution acceleration and labour availability driving record quarterly revenue.Source"Revenue from operations stood at INR1,113 crores in Q2 FY27, registering growth of 58% year-on-year... supported by healthy execution across our project portfolio and improved availability of labor and other execution resources." (Transcript, Original Page 3)
Rapid payment cycles on Adani Group contracts mitigating working capital strain.Source"At the same time, the payment cycle remains very efficient, with approximately 75% of our bills cleared within 7 to 10 days and the remaining 25% generally cleared within the following month." (Prahaladbhai Patel, Transcript, Original Page 7)
Partial recovery of legacy Uttar Pradesh medical college project receivables.Source"Whatever money was lying in the pool was about INR20 crores to INR25 crores we have already received INR810 crores [Hetal Patel confirms INR 20-25 crores received of roughly INR 40 crores]." (Transcript, Original Pages 11-12)
Headwinds
EBITDA margin contraction YoY due to lower-margin Adani business and initial RCC structural project phase.Source"EBITDA margin is at 6.21%, which was 7.10% similar earlier quarter." (Transcript, Original Page 5); "At present, most of our projects are in the structural execution stage, where the RCC structure accounts for around 30% of the overall project scope. During this phase, the overhead absorption is relatively lower, which impacts margins." (Prahaladbhai Patel, Transcript, Original Page 12)
Expected credit loss provisions and doubtful advance write-offs impacting profitability.Source"The provision for doubtful advance was INR8.1 crores as stated in the cash flow statement for H1... Hetal Patel: ...wherever we see that, the advance or the receivables are down, we should be providing around INR8 crores." (Transcript, Original Pages 13, 15)
Surat Diamond Bourse receivables of INR 90 crores remain stalled without timeline for resolution.Source"No, there is no commitment from their side again... Okay. And SDB amount is INR90 crores, it stays as it is? Prahaladbhai Patel: Yes." (Transcript, Original Pages 11, 12)
New businesses and products
capacity expansion · Underway / progressing
Precast capacity enhancement
Expected benefit
Faster project execution, consistent quality, higher throughput, and revenue capacity increase up to INR 250 crores from current full utilization.
Risks
Under-absorption of capex if order pipeline slows; client adoption limits outside internal/captive projects.
Timeline
Ongoing
Investment
INR 5 crores to INR 10 crores for small machines and molds (sheds/infrastructure already ready)
Source"Given the demand visible across building and infrastructure projects, we are progressing with capacity enhancement at our precast facility." (Transcript, Original Page 4); "That is INR250 crores... presently we are operating at full potential... it will be in the range of INR5 crores to INR10 crores." (Transcript, Original Page 13)
Things to check
Extreme client concentration with Adani Group comprising 72% of the order book.Source"Of the total order book within group projects account for approximately 72% (INR9,229) crores..." (Transcript, Original Page 3); "Adani Infra acquired a 34.41% stake in PSP Projects through the Open Offer and Share Purchase Agreement (SPA) and joined the promoter group..." (Investor Presentation, Original Page 21)
Persistent non-recovery of INR 90 crore dues from Surat Diamond Bourse without resolution timeline.Source"No, there is no commitment from their side again... And SDB amount is INR90 crores, it stays as it is? Prahaladbhai Patel: Yes." (Transcript, Original Pages 11, 12)
High working capital tie-up reflected in substantial unbilled revenue and trade receivables.Source"Net unbilled revenue is INR632 crores. Trade receivable is INR809 crores." (Hetal Patel, Transcript, Original Page 5)
How the call went
The call was candid and informative. Management acknowledged lower margins on Adani work and unresolved SDB receivables, but gave transparent operational metrics on workforce, billing timelines, and pipeline visibility.
Specific or vague
Management provided detailed metrics on order book mix (72% Adani/group), bid pipeline (INR 7,800 cr), workforce numbers (23,000-25,000), capex breakdown, and billing days.
Candour
High candour regarding lower project margins on Adani contracts (acknowledged at 5.5-5.7% structural level) and admitting that Surat Diamond Bourse resolution has zero commitment yet.
The hard questions
Analysts probed deeply into the margin dilution caused by Adani contracts, unbilled revenue surges, repetitive ECL/doubtful advance provisions, and stalled legacy receivables.
What analysts pressed on
EBITDA margin capping at ~6.2-7% due to the heavy mix of lower-margin Adani projects.
Recovery status of INR 90 crore stuck in Surat Diamond Bourse.
Sharp expansion in unbilled revenue (INR 632 crores) and trade receivables (INR 809 crores).
Repeated quarterly provisions/write-offs under expected credit loss (ECL) and doubtful advances.
Answers that sidestepped
Detailed project-specific identity behind the INR 8.1 crore doubtful advance provision was deflected to general balance sheet aging commentary.
Adani-specific revenue share for the quarter was not disclosed directly on the call, deferred to offline reporting.
Numbers against the story
Management's narrative emphasizes high-growth nation-building, fast execution, and technology advantages via precast. However, the financial numbers show significant gross margin and EBITDA margin compression (EBITDA margin falling from 7.10% in Q2 FY26 to 6.21% in Q2 FY27) as high-growth Adani group projects operate on cost-plus low single-digit margins (5.5%-5.7%), limiting overall operating profitability despite a 58% surge in revenues.
Figures: the company’s results filing with NSE, linked under the table.
Notes written by gemini-3.8-flash from the documents above on 15 November 2026. They summarise what the company said and can contain mistakes: check the source passage before relying on a point. Not investment advice.