Q2 FY27 · NSE: PARACABLES

Paramount Communications

Results filed 26 October 2026 · Market cap ₹2,011 crore · PE 28

GrowthGuidance maintainedTranscript read

Revenue
+30.9%
on a year ago
EBITDA
+559.8%
on a year ago
Profit to shareholders
+83.1%
on a year ago
EBITDA margin
7.3%
+0.7 pts on last quarter

Paramount Communications reported Q2 FY27 revenue of INR 560.4 crores, representing a 31.1% YoY growth, with operating margin recovering to 7.3%. Growth was led by domestic power cables and the ongoing normalization of U.S. exports following the strike-down of IEEPA tariffs. Execution on the INR 300 crore Narmadapuram greenfield project remains on schedule for partial commissioning in Q1 FY28 to support higher-voltage cables and HTLS conductors.

Paramount Communications Limited, Q2 FY27₹ crore, consolidated
Q2 FY27Q1 FY27vs previous quarterQ2 FY26vs a year ago
Revenue560529+5.9%428+30.9%
Operating profit (EBIT)36.4830.31+20.4%2.27+1507.0%
Operating margin6.5%5.7%+78 bps0.5%+598 bps
Other income3.83.09+23.0%19.64−80.7%
Exceptional items00–0–
Profit before exceptional items and tax32.3926.54+22.0%17.8+82.0%
Profit to shareholders24.2419.7+23.0%13.24+83.1%
Earnings per share (₹)0.740.64+15.6%0.43+72.1%

Source: Paramount Communications Limited’s filing to NSE, 26 October 2026. Operating profit is revenue less every expense except interest, so it leaves out other income and exceptional items. n.m.: not meaningful, because the earlier figure was zero or negative, or the latest one is a loss.

What stood out

  • Sharp recovery in operating profitability following the removal of US IEEPA tariffs
    SourceOperating margin expanded by 600 bps YoY to 7.3% in Q2 FY27 from 1.3% in Q2 FY26, with management noting that U.S. Supreme Court struck down IEEPA tariffs in February 2026 (Transcript Original Page 9, Presentation Page 25).
  • Significant order book buildup in high-margin HTLS conductors
    SourceHTLS order book reached INR 200+ crores as on date, addressing an estimated INR 50,000 crore 5-year reconductoring market in India (Transcript Original Page 5, Presentation Page 21).
  • Discrepancy in management commentary regarding peak debt-to-equity expectations for the capex program
    SourceCFO Shambhu Agarwal stated, 'we don't expect debt-to-equity ratio of more than 0.6 or 0.7', which was immediately corrected by President Marketing Parth Aggarwal stating 'once the plant becomes operational, we are confident that our debt equity ratio shall not cross 0.3' (Transcript Original Page 18).

Guidance

MetricGuidancePeriod
FY27 Revenue Growth
SourceParth Aggarwal: 'our growth will be between 15% to 20% from the previous year sales. We are confident of achieving that' (Transcript Original Page 13).
15% to 20% YoY growth from previous year salesFY27
Operating Margin
SourceSanjay Aggarwal: 'The target of around 8% is not that far away... By Q4, definitely' (Transcript Original Pages 13, 14).
Reach/exceed FY25 operating margin (~8%) by Q4 FY27Q4 FY27
Exports Share
SourceSanjay Aggarwal: 'We expect U.S. exports to constitute 25% to 30% of our revenues for the full FY27' (Transcript Original Page 6).
25% to 30% of total revenueFY27
Net Working Capital Days
SourceSanjay Aggarwal: 'We expect it to normalize in H2 within 90 to 100 days for FY27' (Transcript Original Page 6).
90 to 100 daysH2 FY27
Narmadapuram Revenue Contribution
SourceSanjay Aggarwal: 'revenue of approximately INR 500 crores in FY28, scaling up to INR 1,200 crores in FY29' (Transcript Original Page 7).
INR 500 crores in FY28 and scaling to INR 1,200 crores in FY29FY28 - FY29
Long-Term Revenue Ambition
SourceSanjay Aggarwal: 'We remain firmly focused on our 5-year vision of reaching revenues of INR 5,000 crores by FY31' (Transcript Original Page 7).
INR 5,000 crores revenueFY31

Guidance reiterated on full-year revenue growth (15-20%), target to restore FY25 margin levels by Q4, and Narmadapuram execution timelines.

Tailwinds

  • Strong demand across domestic infrastructure, power transmission, and data centers
    SourceDomestic revenue reached INR 402.3 crores (71.8% of revenue), led by power cables at 55.9% and India B2B + PSU growing 65.1% YoY to INR 349 crores (Transcript Original Page 6, Presentation Page 17).
  • U.S. export normalization restoring competitive parity
    SourceExport revenues stood at INR 158.1 crores (28.2% of total revenue) as Indian cables achieved tariff parity with competing Asian and European countries post-IEEPA tariff repeal (Transcript Original Pages 4, 6).
  • Tight discipline on raw material procurement against price volatility
    SourceManagement restricts firm-price orders to 3-4 months delivery and books metals the next working day after receiving orders to insulate margins (Transcript Original Pages 3-4, 11).

Headwinds

  • Elongated working capital cycle due to front-loaded supplier payments
    SourceNet working capital stood at 108 days versus 101 days at FY26 end due to accelerated supplier payments following equity raise (Transcript Original Page 6, Presentation Page 27).
  • Extended approval cycles for high-voltage cable lines
    SourceManagement noted approvals for 132 kV and 220 kV cables will take 1 to 1.5 years post commissioning, requiring initial plant utilization on lower-voltage cables (Transcript Original Pages 7, 12).
  • Volatile metal input environment with copper reaching record highs
    SourceCopper prices touched record highs during the quarter amid U.S. tariff decisions and mine supply disruptions, though partially offset by softer aluminum (Transcript Original Pages 3-4).

New businesses and products

capacity expansion · Foundation and civil works underway; orders for critical machinery placed

Narmadapuram Greenfield Manufacturing Facility

Expected benefit
Doubling existing capacity by adding ~30,000 MTPA by FY30; revenue generation of ~INR 500 crores in FY28 and scaling to ~INR 1,200 crores in FY29
Risks
Lead times for 132 kV and 220 kV cable product approvals take 1 to 1.5 years
Timeline
Partial commissioning in Q1 FY28
Investment
INR 300 crores
SourceTranscript Original Pages 6, 7, 12, 17; Presentation Pages 15, 23

new product · Commercialized and indigenously developed (IDDM); carbon-core and gap-type up to 765 kV

HTLS (High Temperature Low Sag) Conductors

Expected benefit
Double-digit margin profile; addressing INR 50,000 crore market opportunity in 5 years
Risks
Execution timelines involve installation/EPC work, resulting in potentially longer delivery schedules
Timeline
Active order execution; capacity augmentation at Narmadapuram in FY28
Investment
Included in Narmadapuram capex
SourceTranscript Original Pages 4, 9, 10, 12; Presentation Page 21

new business · Approvals established with leading developers; further approvals progressing

Data Centre Cable Portfolio

Expected benefit
Supply of power and specialized cables to high-growth hyperscale and colocation capex projects
Risks
Customer credentialling and long approval lead times
Timeline
Ongoing
SourceTranscript Original Pages 4, 15; Presentation Page 22

Things to check

  • Year-ago margin under 5%: growth from a low base
  • Internal contradiction on leverage guidance during capex execution
    SourceCFO guided for long-term borrowings resulting in a debt-to-equity ratio of up to 0.6x to 0.7x, which was contradicted by the President of Marketing stating it will not exceed 0.3x (Transcript Original Page 18).

How the call went

The call was informative with granular operational data, but leadership appeared guarded on technical details in HTLS and showed visible internal misalignment between the CFO and Marketing President on peak debt-to-equity levels.

Specific or vague
Management provided clear metrics for order book composition, working capital days breakdown, and Narmadapuram commissioning timelines and revenue ramp-up.
Candour
Open about the severity of the prior year's tariff shock and past strategic decisions to exit smaller export geographies; however, confusion emerged between the CFO and President Marketing on debt leverage limits.
The hard questions
Analysts probed into capacity run rates before greenfield commissioning, steady-state margins ex-clawbacks, and specific technological variants of HTLS conductors.

What analysts pressed on

  • Whether the 3-4 month order book provides sufficient long-term revenue visibility
  • Impact of product qualification and approval delays on the Narmadapuram revenue ramp-up
  • Margin sustainability once potential US tariff clawback adjustments are excluded
  • Peak debt levels required to fund the INR 300 crore capex

Answers that sidestepped

  • Deflected questions regarding specific HTLS technologies (APC vs AECP) stating 'These are basically brands, not technologies, and these are probably areas where we would not like to discuss on a public forum' (Transcript Original Page 17).
  • Refused to specify tonnage-wise capacity for HTLS post greenfield commissioning, deferring it until the plant becomes operational (Transcript Original Page 17).

Numbers against the story

Management's narrative emphasizes strong operational recovery from the FY26 tariff shock, which is corroborated by operating margins expanding from 1.3% in Q2 FY26 to 7.3% in Q2 FY27 and revenue up 31.1% YoY to INR 560.4 crores. However, while narrative points to tight working capital discipline, net working capital days expanded to 108 days (vs 101 days in FY26) due to cash outflow for accelerated trade payables.