Smart Equity Invest

← Results dashboard

Q2 FY27 · NSE: NHPC

NHPC

Results filed 5 November 2026 · Market cap ₹76,172 crore · PE 17.6

GrowthGuidance maintainedTranscript read

Revenue
+33.2%
on a year ago
EBITDA
+41.9%
on a year ago
Profit to shareholders
+51.7%
on a year ago
EBITDA margin
64.2%
+2.4 pts on last quarter

NHPC delivered strong Q2 FY27 performance with revenue up 33% YoY to ₹4,482 crore and reported PAT up 52% YoY to ₹1,549 crore, bolstered by the part-commissioning of Subansiri Lower, full resumption of Teesta-V, and Parbati-II turning profitable. Operational gains were partially offset by a doubling of finance costs and depreciation following asset capitalization, a sharp drop in secondary energy incentives, and a ₹231 crore provision for Teesta-IV. Management reiterated full-year capex targets of ₹14,300 crore and guided for EBITDA to reach approximately ₹10,000 crore as 1,744 MW of hydro projects come online across FY27.

NHPC Limited, Q2 FY27₹ crore, consolidated
Q2 FY27Q1 FY27vs previous quarterQ2 FY26vs a year ago
Revenue4,4833,808+17.7%3,365+33.2%
Operating profit (EBIT)2,2661,753+29.3%1,585+42.9%
Operating margin50.5%46.0%+453 bps47.1%+343 bps
Other income187151+23.5%265−29.3%
Exceptional items00–0–
Profit before exceptional items and tax1,8971,298+46.1%1,572+20.6%
Profit to shareholders1,5491,096+41.4%1,021+51.7%
Share of joint ventures' and associates' profit0.951.2−20.8%0.09+955.6%
Earnings per share (₹)1.541.09+41.3%1.02+51.0%

Source: NHPC Limited’s filing to NSE, 4 November 2026. Operating profit is revenue less every expense except interest, so it leaves out other income and exceptional items. n.m.: not meaningful, because the earlier figure was zero or negative, or the latest one is a loss.

What stood out

  • Significant capacity additions nearing completion across hydro projects totaling over 1,700 MW in FY27
    SourceManagement stated: 'this year we are going to commission 1,744 MW (500 MW Subansiri already commissioned) – 500 MW from Subansiri, then 624 MW from Kiru and 120 MW from Rangit' (Transcript, page 20).
  • One-off impairment provision of ₹231 crore taken for Teesta-IV Project impacting Q2 bottom line
    Source'only one provision we have made in this Q2, which is Rs. 231 Crore regarding Teesta-IV. So, if you add back this Rs. 231 Crore entirely to the reported PAT, you will arrive at the adjusted PAT' (Saroj Kumar Roy, Transcript, pages 9, 12-13).
  • Operational turnaround and restart of key stations (Parbati-II and Teesta-V) added ₹480 crore incremental PBT YoY
    Source'last year Parbati-II was having a loss of Rs. 164 Crore and this quarter Parbati has given Rs. 215 Crore PBT... Teesta-V has generated 859 MUs... PBT contributed by Teesta-V is Rs. 100 Crore' (Saroj Kumar Roy, Transcript, pages 12, 17-18).

Guidance

MetricGuidancePeriod
Consolidated Capex
Source'This year also, we have capex target of Rs. 14,300 Crore and till now, we have already achieved Rs. 6,500 Crore approx... Next year onward, on an average you can consider Rs. 14,000 - Rs. 15,000 Crore approx. capex on consol level' (Saroj Kumar Roy, Transcript, pages 20-21).
₹14,300 crore for FY27; ₹14,000 - ₹15,000 crore annually for subsequent yearsFY27 and onward
EBITDA Run-rate
Source'post-commissioning of Subansiri Lower full year basis, Pakal Dul, etc, our EBITDA is also going to reach at Rs. 10,000 Crore approx.' (Saroj Kumar Roy, Transcript, page 19).
₹10,000 crore approximately post-commissioning of Subansiri Lower and Pakal DulPost full commissioning (FY28 onwards)
PAT Target
Source'By FY’28, we are targeting to generate PAT level of Rs. 6,000 Crore - 6,400 Crore approx.' (Saroj Kumar Roy, Transcript, page 21).
₹6,000 - ₹6,400 croreFY28
Capacity Commissioning
Source'this year we are going to commission 1,744 MW... Then next year FY’28 - 250 MW Subansiri is coming, 1,000 MW Pakal Dul is coming' (Saroj Kumar Roy, Transcript, page 20).
1,744 MW to be commissioned in FY27 (500 MW Subansiri remaining, 624 MW Kiru, 120 MW Rangit-IV); 1,250 MW in FY28 (250 MW Subansiri, 1,000 MW Pakal Dul)FY27 - FY28

Tailwinds

  • Part commissioning of Subansiri Lower Project (1,250 MW commissioned across 5 units) drove substantial revenue and generation volume
    Source'Subansiri Lower Project, which now stands at 1,250 MW commissioned... generated around 300 MUs higher than the proportionate design energy... Subansiri has added Rs. 132 Crore approx. profit in Q2' (Transcript, pages 2, 13).
  • Resumption of Teesta-V commercial operations following post-flood restoration
    Source'Teesta-V Power Station which got damaged due to the October’23 flash flood... restoration was completed and the power station has started the commercial operation again from July’26... PBT contributed by Teesta-V is Rs. 100 Crore' (Transcript, pages 5, 12).
  • Turnaround of Parbati-II to profitability
    Source'last year Parbati-II was having a loss of Rs. 164 Crore and this quarter Parbati has given Rs. 215 Crore PBT' (Saroj Kumar Roy, Transcript, page 17).
  • Reduction in generation expenses due to lower water cess and favorable High Court ruling
    Source'Generation Expenses have come down from Rs. 302 Crore to Rs. 277 Crore... due to lower water cess on account of lower generation in... J&K and no water cess for power station situated in Uttarakhand in view of verdict of Hon’ble High Court' (Mahesh Kumar Sharma, Transcript, pages 8-9).

Headwinds

  • Higher finance costs and depreciation charged to P&L following Subansiri Lower capitalization
    Source'Finance Cost from Rs. 278 Crore to Rs. 556 Crore... mainly due to increase on account of interest on loan related to Subansiri Lower Project charged to P&L... Depreciation & Amortization Expenses have gone up from Rs. 441 Crore to Rs. 610 Crore' (Mahesh Kumar Sharma, Transcript, pages 8-9).
  • Sharp drop in incentive earnings, primarily from secondary energy incentives
    Source'total incentive position of Q2 FY’27 is Rs. 59 Crore as against Rs. 253 Crore in the corresponding previous period. Secondary Energy has decreased by Rs. 204 Crore i.e. 89% decrease' (Mahesh Kumar Sharma, Transcript, pages 9-10).
  • Grid connectivity issues causing delays across under-construction solar projects
    Source'There is some issue of connectivity that's why these projects are getting delayed... But connectivity issues are there which all the solar projects are facing' (Bhupender Gupta, Transcript, page 6).
  • Unsold renewable bids / untied PPAs due to discom reluctance to sign long-term vanilla solar contracts
    Source'We have tendered out in NHPC around 23,120 MW... PPA has been signed only for 9,000 MW... around 5,000 MW capacity is there which may not be tied up... states are slightly like reluctant as of now to commit for 25 years' (Bhupender Gupta, Transcript, page 17).

New businesses and products

new business · Tendering initiated; awaiting final nod from government

Indira Sagar - Omkareshwar Pumped Storage Project (640 MW)

Expected benefit
Regulated return project; tariff estimated below ₹4.90 - ₹5.00/unit
Risks
PPA with Government of M.P. is still under discussion and yet to be finalized
Timeline
Physical work commencement targeted in FY27
Investment
₹5,200 crore approximately
SourceBhupender Gupta: 'Rs. 5,200 Crore approx. is the cost. Tariff will be less than Rs. 5 - Rs. 4.9/unit... tendering process has already been initiated' (Transcript, pages 6, 22).

capacity expansion · CCEA approved; subsidiary formation and environmental/forest clearances in progress

Kamala Hydro Electric Project (1,720 MW)

Expected benefit
Large-scale hydro generation in Arunachal Pradesh
Risks
Forest/environmental clearance pending and land acquisition underway
Timeline
Targeting physical work start at site during FY27
Investment
₹26,070 crore
SourceBhupender Gupta: 'CCEA has approved investment of Rs. 26,070 Crore for construction of Kamala HEP... We are targeting to start the physical work at site during this financial year' (Transcript, pages 5, 14).

capacity expansion · Transferred from SJVN; clearances in place; PIB initiated; tendering run in parallel

Etalin Hydro Electric Project (3,097 MW)

Expected benefit
Will be one of the largest hydro projects in India
Risks
Pending PIB and Cabinet/CCEA approvals; ₹800 crore consideration payable to SJVN post-PIB
Timeline
Cabinet approval expected in 2-3 months; work to start physically in FY27
Investment
Consideration to SJVN is ~₹800 crore; total project cost not specified
SourceBhupender Gupta: 'Etalin (3,097 MW)... got all the clearances... tendering and hopefully, we will get the cabinet approval maybe within two months' (Transcript, pages 6, 14-16).

capacity expansion · Under execution (300 MW Bikaner commissioned, remaining under implementation)

Grid-Connected Solar Projects (CPSU Scheme & Solar Parks: 1,190 MW under construction)

Expected benefit
Diversification into renewable energy
Risks
Interconnection and grid connectivity delays
Timeline
Commissioning between December 2026 and November 2027
Investment
Not specified
SourceBhupender Gupta: '1,190 MW capacity is under construction and this will be 100% completed next year... delayed due to the availability of the connectivity' (Transcript, pages 6, 16).

Things to check

  • ₹5,000 MW of renewable bids awarded via REIA lack signed PPAs as states show reluctance to commit long term
    Source'Out of that, we have awarded 73 projects. PPA has been signed only for 9,000 MW... So around 5,000 MW capacity is there which may not be tied up... states, they are slightly like reluctant as of now to commit for 25 years' (Bhupender Gupta, Transcript, page 17).
  • Significant project cost already incurred on Teesta-IV against which an impairment provision of ₹231 crore was booked this quarter
    Source'Provision related to Teesta-IV Project of Rs. 231 Crore' (Mahesh Kumar Sharma, Transcript, page 9).

How the call went

Management demonstrated strong technical and financial command, offering transparent unit-by-unit operational updates, exact PBT breakdowns, and pragmatic commentary on renewable off-take dynamics.

Specific or vague
Management provided detailed project-level completion percentages, expenditure incurred vs budget, PBT contributions by individual power stations, and clear capex targets.
Candour
Management was forthright about grid connectivity bottlenecks delaying solar projects, unwillingness of Discoms to enter 25-year PPAs for untied renewable capacity, and the ₹231 crore impairment provision on Teesta-IV.
The hard questions
Tough questions around leverage (₹59,000 crore debt), tariff petition approvals for Subansiri/Parbati-II, and untied solar PPAs were answered with clear operational vs under-construction breakdowns and regulatory updates.

What analysts pressed on

  • Status and timeline of final CERC tariff orders and unbilled revenues for Parbati-II and Subansiri Lower.
  • High balance-sheet leverage (debt around ₹59,000 crore against EBITDA of ~₹7,000 crore) and debt service burden.
  • Spike in trade receivables at half-year end (₹4,283 crore vs ₹2,630 crore in March 2026).
  • Power evacuation and grid transmission availability for massive upcoming capacity in Arunachal Pradesh.

Numbers against the story

Management's narrative of robust operational rebound matches the numbers, with sales growing 33.2% YoY to ₹4,483 crore and EBITDA margins expanding by 391 bps YoY to 64.15%, propelled by 1,250 MW part-commissioning at Subansiri Lower, restoration of Teesta-V (₹100 crore PBT), and Parbati-II turnaround (₹215 crore PBT). However, as flagged in the narrative, the capitalization of Subansiri units drove finance costs up 100% and depreciation up 38% YoY, while secondary energy incentives plunged by 89% YoY.

Sources

Notes written by gemini-3.8-flash from the documents above on 15 November 2026. They summarise what the company said and can contain mistakes: check the source passage before relying on a point. Not investment advice.